KnowledgeMaps Work Breakdown Structure

Expand Diagram
Strategic Analysis Decision on Strategy and Goals Define Requirements, Prepare Technical Specification Determine "as-is" Condition Vendor Selection and Contract Award Procurement Process Prototype Select Prototype Theme Production Release Implementation Project Management Definition
Develop "should-be" Concept Detail Professional and Technical Requirements Vendor Evaluation Define Basis for Decision Implementation User Training Quality Assurance Start Supervision
Prepare Technical Specification Compile Catalog of Requirements Select Best Vendor Generate Contract End

Software creation

Cost130.300,00 €
Completion47 %
Risk37 %
Duration01.01.2006 - 31.12.2006

Strategic Analysis

PSP-Code1
Cost3.000,00 €
Completion70 %
Risk20 %
Duration01.01.2006 - 01.02.2006

Decision on Strategy and Goals

PSP-Code1.1
Cost3.000,00 €
Completion70 %
Risk20 %
Duration01.01.2006 - 01.02.2006

Define Requirements, Prepare Technical Specification

PSP-Code2
Cost17.000,00 €
Completion40 %
Risk44 %
Duration01.02.2006 - 07.04.2006

Determine "as-is" Condition

PSP-Code2.1
Cost1.000,00 €
Completion30 %
Risk50 %
Duration01.02.2006 - 20.02.2006

Develop "should-be" Concept

PSP-Code2.2
Cost4.000,00 €
Completion80 %
Risk30 %
Duration20.02.2006 - 31.03.2006

Detail Professional and Technical Requirements

PSP-Code2.3
Cost3.000,00 €
Completion20 %
Risk70 %
Duration14.03.2006 - 07.04.2006

Prepare Technical Specification

PSP-Code2.4
Cost7.000,00 €
Completion10 %
Risk50 %
Duration01.02.2006 - 31.03.2006

Compile Catalog of Requirements

PSP-Code2.5
Cost2.000,00 €
Completion60 %
Risk20 %
Duration01.03.2006 - 31.03.2006

Vendor Selection and Contract Award

PSP-Code3
Cost7.000,00 €
Completion46 %
Risk40 %
Duration01.01.2006 - 12.03.2006

Procurement Process

PSP-Code3.1
Cost1.500,00 €
Completion70 %
Risk50 %
Duration01.01.2006 - 31.01.2006

Vendor Evaluation

PSP-Code3.2
Cost500,00 €
Completion30 %
Risk10 %
Duration02.02.2006 - 25.02.2006

Define Basis for Decision

PSP-Code3.3
Cost1.500,00 €
Completion60 %
Risk40 %
Duration20.02.2006 - 28.02.2006

Select Best Vendor

PSP-Code3.4
Cost500,00 €
Completion50 %
Risk20 %
Duration26.02.2006 - 27.02.2006

Generate Contract

PSP-Code3.5
Cost3.000,00 €
Completion20 %
Risk80 %
Duration02.03.2006 - 12.03.2006

Prototype

PSP-Code4
Cost5.300,00 €
Completion60 %
Risk40 %
Duration01.04.2006 - 30.04.2006

Select Prototype Theme

PSP-Code4.1
Cost500,00 €
Completion70 %
Risk10 %
Duration01.04.2006 - 05.04.2006

Implementation

PSP-Code4.2
Cost4.800,00 €
Completion50 %
Risk70 %
Duration05.04.2006 - 30.04.2006

Production Release

PSP-Code5
Cost82.500,00 €
Completion30 %
Risk37 %
Duration01.04.2006 - 31.12.2006

Implementation

PSP-Code5.1
Cost70.000,00 €
Completion20 %
Risk80 %
Duration01.04.2006 - 30.09.2006

User Training

PSP-Code5.2
Cost7.500,00 €
Completion10 %
Risk10 %
Duration14.08.2006 - 31.12.2006

Quality Assurance

PSP-Code5.3
Cost5.000,00 €
Completion60 %
Risk20 %
Duration01.06.2006 - 03.08.2006

Project Management

PSP-Code6
Cost15.500,00 €
Completion38 %
Risk40 %
Duration01.01.2006 - 31.12.2006

Definition

PSP-Code6.1
Cost2.000,00 €
Completion70 %
Risk50 %
Duration01.01.2006 - 01.02.2006

Start

PSP-Code6.2
Cost1.500,00 €
Completion30 %
Risk10 %
Duration02.02.2006 - 10.02.2006

Supervision

PSP-Code6.3
Cost10.000,00 €
Completion40 %
Risk20 %
Duration01.01.2006 - 31.12.2006

End

PSP-Code6.4
Cost2.000,00 €
Completion10 %
Risk80 %
Duration12.12.2006 - 31.12.2006

Page Views
Visitors today
Average visitors per day
Visitors since
KnowledgeMaps
Work Breakdown Structure
Expand Diagram
Strategic Analysis
Decision on Strategy and Goals
Define Requirements, Prepare Technical Specification
Determine "as-is" Condition
Vendor Selection and Contract Award
Procurement Process
Prototype
Select Prototype Theme
Production Release
Implementation
Project Management
Definition
Develop "should-be" Concept
Detail Professional and Technical Requirements
Vendor Evaluation
Define Basis for Decision
Implementation
User Training
Quality Assurance
Start
Supervision
Prepare Technical Specification
Compile Catalog of Requirements
Select Best Vendor
Generate Contract
End